Sydney Metro Parramatta Station: Hydro Demolition from an EWP to Expose Diaphragm Wall Couplers
Following our work at Rosehill Station, Gamuda Australia and Laing O'Rourke Consortium (GLC) brought Water Jetting Solutions in for handheld hydro demolition on the diaphragm walls at Sydney Metro – Parramatta Station. We prepared areas of the walls for patch repairs and exposed the cast-in couplers, working from an elevated work platform (EWP) up the face of the station box.

Project snapshot
Client: Gamuda Australia and Laing O'Rourke Consortium (GLC)
Project: Sydney Metro – Parramatta Station, NSW
Dates: July to August 2026
Scope: Handheld hydro demolition for patch repairs and coupler exposure on diaphragm walls
Equipment: Hammelmann HDP200 trailer pump, handheld UHP lances, EWP
Crew: Three-person crew
Safety: Completed with no safety incidents
Why hydro demolition
The couplers and reinforcement in the walls had to stay undamaged for the next stage of the structure. Ultra-high-pressure (UHP) water removes the concrete without vibration or impact, so the steel comes out clean and intact, and the surface left behind is rough and sound, ready for the patch repairs to bond to.
How we did it
We set up a Hammelmann HDP200 trailer pump in the station box and worked the walls with handheld UHP lances from an EWP, which gave the operator safe, flexible access along and up the wall face. As at Rosehill, the pump operator couldn't see the lance operator from the pump, so we ran a three-person crew to keep clear communication between the pump and the work face at all times.

The result
The work was completed with no safety incidents, giving GLC clean, undamaged couplers and repair-ready surfaces. It was our second Sydney Metro station in a row, building on the same method and crew set-up we refined at Rosehill.